Recently, I was helping a bank define Basel 2 requirements.
For every dollar a bank lends, at least 8 cents should come from its own pocket, and the rest from its depositors. But a risky $1 loan may be like a $1.5 loan, whereas a $1 Government loan may be like a $0.5 loan. This is the "risk-weighted asset" (RWA) value. Basel 2 says 8% of risk-weighted assets should come from the bank's pocket.
I was trying to convince the people who were maintaining the leasing software that the RWA of a lease is the NPV of its future cash flows, and they had a whole lot of questions.
"What is this NPV?"
You can put 90 cents in the bank today at 11% and get $1 next year. So $1 next year is worth 90 cents today. When a customer pays $100 over the next 10 months, it's worth less than $1000 today. That's the NPV. The NPV is what you put in the bank today to get that cash flow: $100 over the next 10 months
"So why should we use NPV for leases?"
That's because when a lease is cancelled, the closure payment is the NPV. If you take a lease for 10 months at $100 a month, this includes the interest. If you terminate the lease after 5 months, you won't pay $500 for the remaining 5 months. You'll pay less -- the NPV of those $100 for 5 months. So there is some logic to using NPV as the RWA.
"OK, so how do we calculate the NPV?"
You divide each cash flow by (1 + r)^n, where r is the internal rate of return, and n is the number of years. Then you add them up. You'll get a number less than the sum of cash flows.
"And how do we calculate this IRR?"
(sheepishly) The IRR is that interest rate for which the NPV is zero.
And we got stuck here, because their software didn't have an IRR function, and the definitions for IRR and NPV are circular.
To do this in Excel is simple. Just enter the cash flow values. So, if on a cash loan of $500, you paid $100 for 6 months, and use the IRR function, as shown below. Your monthly IRR is 5.47%.
But we needed their AS/400 system to do it as well, and it didn't have the IRR function.
After a few weeks of digging around, I found a paper that said you can calculate the IRR iteratively. Let
- npv be the NPV given an IRR and cash flows
- sum be the sum of cash flows
- p be the principal amount
Then irr = irr * log(p/sum) / log(npv/sum) is the iteration you need to successively apply.
We decided to start with 1.85 times the stated interest rate (which was a pretty good guess for most leases), and kept applying this formula until it stays more or less the same. Worked like a charm.
Here's the spreadsheet with the calculation.
Comments
Had a question regarding building a cashflow table when only IRR and the initial outlay are stated along with the period.
The project has an $80,000 investment outlay and is expected to yield an IRR of 30% over a 5 year economic life and the investment outlay is depreciated on a straight line basis towards a zero estimated salvage value
Could you please help me with this?
Thanks
Thank You
have used a monthly IRR in the example, and you’re right in pointing out
that it makes things a little confusing. Please replace “month” with “year”
right through the article, and I believe it would read right then.
However I want to know how annual interest is 4627 when the sum of 8792 x12 months = 105504 and the difference between the principal amount = 5,504.
Can you explain?
Su
just happens to be 100000 at the beginning. After making the first
payment of 8792, the principal reduces, and it’s not easy to find out
how much of that 8792 was for the principal, and how much of it was
for the interest. That’s what the article tries to explain.